Sanctuary Work Progressing

Send to friendClick here for Printer-friendly - Whole Page ViewClick here for Printer-friendly - Whole Page View

The picture to the left shows several elements under construction on our new Sanctuary. 

  • The steel for the covered drop off area is in place. The posts will be brick covered and the roof will be pitched like the gable above it.
  • With the finish of the south wall the brick work is nearing completion.  Only details like stone caps and cleaning remain to be finished.
  • The roof work is progressing.  You can see the workers putting into place the standing seam metal roof on the south side of the sanctuary roof. With the completion of the roof work, dry walling will begin soon on the interior.